Thursday, August 11, 2011

Day 15 8/1/11

Time is proving to be hard to find lately as August is our busy month on the personal side.  Today I picked up the 3 remaining windows that were ordered through the Millwork outlet center.  They were custom sizes to maximize the available space in the loft area.  From the inside, the dormer windows almost feel like port holes.  Atleast they will let in natural light.

I also installed the door.  We decided to go with a metal door.  We considered using a wood door to continue with the cabin theme style.  The price for the the wood door was a little more than we wanted to spend.  The costs are starting to add up and we are trying to evaluate each purchase with a slightly more flexible criterea.

I only worked about 3 hours today (94 total hours worked)